July 7, 2006
Construction Daily
The architect completed inserting the new engineering data into the plans, and is putting the revised copies in the mail to Richard at Hawes office. Next steps are for Richard to take the plans back to the engineer for his seal, then off to the county to apply for the building permit.
Heard from Josh at the timber frame company. They are appropriately nervous about the timeline slipping again, as originally they were to arrive on July 17 but the engineering delays precluded that. Now we are scheduled for an August 14 frame installation, but given the uncertainty of the permit application process and not to mention potential weather delays we are all feeling a little tense...
Posted by Stephen at July 7, 2006 2:21 PM