Today I focused my attention on cleaning out the master suite. Not fun scraping all the glue and drywall mud off the floor, but it was nice to finally get a look at the size of the room without a ton of shit lying around.
The Tops of the Town crew came by to drop of the sections of the counter top. Wow. That's all I can say. This top is going to look so cool. They'll be back on Friday to do the installation.
Vernon and Tim finished up the catwalk railings and will continue on the loft railings tomorrow.
Outside Trevor dug two trenches in the winery for the floor drain plumbing. Glad I didn't see him drive a backhoe into the building, would have had an anxiety attack...
Spent some time in the vineyard installing tensioners for the trellis catch wires.
Daily hours = 10
Total hours = 567